Offshore World - Track Record

Brunei Shell Petroleum

  • Pipeline Restoration Project
  • SKID Field Development Project
  • Mampak Field Development Project
  • CPLQ Jacket Installation
  • Replacement of Main Oil Line
  • Platform Abandonment Project
  • Bugan Field Development Project
Location: Offshore Brunei
Period: 2007-Ongoing
Vessels: Da Li Hao, Swiber Conquest, Swiber Glorious, Swiber Victorious, Aziz
WD: 40-60 meters
Brunei Shell Petroleum Brunei Shell Petroleum

Pipeline Restoration Project (2007-2008)

  • Installation of 18 pipelines 6" OD to 12" OD varying from 1km to 15km long with a total of 43km including 36 stalk-on risers, multiple pipeline crossings and riser clamps in water depths varying from 20m to 48m

Mampak Field Development Project (2007-2008)

  • Installation of Mampak well head platform & Magpie module with 1,500 t deck
  • Installation of 3 pipelines 8" OD to 12" OD with a total of 28km including 6 stalk-on risers and a subsea cable 6.5km long

Replacement of Main Oil Line (2009)

  • Installation of 80km of 24" main oil trunkline from shore to 40m water depth including y-piece and 50m spool tie-ins

Bugan Field Development Project (2009)

  • Installation of Bugan well head platform with 2 pipelines, 4 stalk-on risers and 1 subsea cable

SKID Field Development Project (2010)

  • Installation of SKID well head platform with 3 pipelines, 6 risers and 1 subsea cable

CPLQ Jacket Installation (2010)

  • Installation of 8 legged jacket for new LQ

Platform Abandonment Project (2010)

  • Abandonment of 6 platforms and their disposal
Client: Brunei Shell Petroleum
Project: Transportation & Installation of Offshore facilities for Major Project
Location: Brunei
Period: FY2010-2011
WD: 50 meters

Work Scope:

  • Decommissioning of 4 platforms
  • Installation of 1500 MT, 8 leg Champion 7 LQ jacket including transportation
  • T&I of 1200 MT 4 leg jacket
  • T&I of topside - 700 MT approx.
  • Pipelines - T&I including tie-in, Riser. Crossings for span correction & pre-commissioning
  • 1 x 16” x 14 km
  • 1 x 16” x 14 km
  • 1 x 12” x 9.6 km
  • Cable T&I 1 x 16” x 14 km
Client: Petronas Carigali
Project: Puteri Field Development
Location: Offshore Malaysia
Period: 2007 - 2008
Vessel: Da Li Hao
WD: 61 meters

Work Scope:

  • Transportation and installation of 900 MT jacket, 1,300 MT deck and 2 x 8" x 13 km pipelines in 61 meters water depth
  • Installation of 8 subsea spools and manifold connecting new facilities to existing FPSO system
Client: Petronas Carigali
Project: Abu Cluster Project
Location: Offshore West Malaysia
Period: 2006-2007
Vessel: Da Li Hao, Swiber Conquest
WD: 61 meters

Work Scope:

  • Installation of 6” and 8“ (2km each) pipelines by rentis method in 61m water depth
  • Transportation & installation of 1,200T Jacket using submersible method
  • Transportation and installation of a 2,200 MT deck
  • Transportation and installation of 6-point mooring system for Abu FSO
  • Tow and Hook-Up of Abu FSO and installation of mid-water arch
  • Installation of flexible risers
Client: Kodeco Energy Ltd
Project: Offshore EPCI Services for West Madura and Poleng Fields (KE-32, KE-38 and PPP)
Location: Offshore East Java, Indonesia
Period: 2007-2008
Vessel: Da Li Hao, Swiber Conquest
WD: 55 meters

Work Scope:

Installation of Sub-sea Pipelines (water depth: 5m to 55m)

  • 16” x 22km KE38 Platform to Platform
  • 12” x 7km KE32 Platform to Tie-in point
  • 16” x 48km PPP to Gresik
  • Pipeline installation using Swiber Conquest

Platform Installation (water depth: 55m)

  • Installation of 2 x 250MT wellhead platforms (KE- 32 & KE38)
  • Installation of PPP process platform (1,300MT deck & 1,000MT jacket)
  • Platform installation using the Da Li Hao
Client: Talisman Energy
Project: Block PM 3 Commercial Arrangement Area Northern field Development Project
Location: Malaysia
Period: 2008
Vessel: Da Li Hao
WD: 60 meters

Work Scope:

  • Installation Works for Decks, Pipelines and Spools
  • Installation of wellhead riser platform BO-C (1550MT) and riser platform BO-D (2,040 MT)
  • Installation of 24” x 30km pipeline
  • Installation of tie-in spools
Client: ConocoPhillips Indonesia
Project: North Belut Field Development
Location: Natuna Sea, Indonesia
Period: 2008-2009
Vessel: Da Li Hao, Swiber Conquest, Swiber Victorious
WD: 96 meters

Work Scope:

  • Installation of WHP-D and WHP-C wellhead platforms with jackets weighing 1,800 MT each and the decks weighing 2,200 MT each
  • Installation of CPP jacket weighing 5,600 MT using launch method using newly commissioned launch barge SLB-1
  • Installation of 10” dia, 37km liquid pipeline between NBCPP and Kerisi PLEM
  • Installation of 16” dia, 37km gas pipeline between NBCPP and Kerisi PLEM
  • Installation of 22” dia, 10km multiphase pipeline between NBCPP and WHP-C
  • 18 Subsea Tie-ins in 100m water depth with spools as long as 52m long.
Client: Murphy Oil Malaysia
Project: Murphy Block SK309 & SK311 development
Location: Malaysia
Period: 2008-2009
Vessel: Swiber Conquest
WD: 35 meters

Work Scope:

  • Installation of 2 ea. 24” OD trunklines 36km each from shore to GORA platform
  • Beach pull including shore approach works involving coffer dam installation, Lucker winch set up and pulling pipe to shore
  • Installation of 20” OD x 4km pipeline
  • Installation of 4 infield pipelines 6” and 8” OD total of 31km
  • Pre-commissioning of pipelines
Client: MOGE
Project: Yadana Yangon Domestic Gas Oil Pipeline
Location: Myanmar
Period: 2009-2010
Vessel: Swiber Conquest, Swiber Concorde, and Aziz
WD: 2 - 60 meters

Work Scope:

  • Installation of 150km of 24” pipeline
  • Riser spool installation at Yadana Platform using SAT diving including installation of 50-70m long spools
  • 2 x above water tie-ins in 28m and 6m water depth
  • 1km Beach Pull using Concorde in 4.5m water depth
  • Pre-trenching & back-filling for 6km from land fall point. Used IDN dredger for pre-trench
  • Pre-commissioning of 150km line including drying to -10”C
Client: British Gas India
Project: HYDRA - PK & SWP Project
Location: Panna Field, Offshore India
Period: 2008-2009
Vessel: Swiber Supporter
WD: 39 - 59 meters

Work Scope:

Engineering, Procurement, Construction/fabrication, Transportation, Installation & Pre-Commissioning of:

  • PK Platform, a new 6-slot wellhead platform, jacket 700 MT - Deck 350 MT
  • SWP (South West Panna) Platform, a new 6-slot wellhead platform, jacket 700 MT - Deck 350 MT
  • 1 x 12” x 5.5 km (PK-PPA) and 1 x 14” x 12.1 km (SWP-PPA) production pipeline
  • 2 x 4.5” gas lift pipelines (PPA-SWP & PPA-PK) and 4 x 1.25” chemical injection lines, piggy backed on main pipeline (two each on PPA-SWP & PPA-PK)
  • Installation of risers at PPA and tie-ins at PPA, PK and SWP
Client: British Gas India
Project: Panna Gas Lift Project
Location: Panna Field, Offshore India
Period: 2008-2009
Vessel: Swiber Conquest, Swiber Supporter
WD: 42 - 47 meters

Work Scope:

  • Offshore-Fabrication, Transportation and Installation of 6"x 6.8 km gas lift line pipes, Riser & Tie-in Works
Client: British Gas India
Project: British Gas Pipeline Project
Location: India
Period: FY2010-2011
Vessel: PJW -3000, Swiber Supporter
WD: 39 - 59 meters

Work Scope:

Engineering, Procurement, Construction/ Fabrication with modification, Transportation, Installation & Pre-commissioning of:

  • SWP (South West Panna) Platform modification from 6 slots wellhead platform to 9 slots to renamed as PL Platform with jacket 800MT - deck 350MT;
  • One 14”x 7.5km (PL-PPA) pipeline;
  • Two 4 ½” gas lift pipelines (PL-PPA) and four 1 1/4” chemical injection pipelines (PPA-PL), piggy backed on main pipeline
Client: Vietsovpetro (VSP)
Project: Dai-Hung Structural Installation Project
Location: Vietnam
Period: FY2011
Vessel: Magnificent

Work Scope:

  • Upend & installation of 4000 MT Jacket
  • Installation of 8 skirt pile & drive up to 85m penetration below sea bed, maintain jacket levels within tolerance
  • Removable of 4 buoyancy tanks
  • Installation of 2 boat landings
  • Installation 1 x 1250 MT topside
  • Installation 1 helideck
  • Installation 1 flare boom
  • Hook-up, Touch up painting, & pre- commissioning
Client: ONGC
Project: B-193 Field Development Project
Location: Offshore Mumbai, India
Period: 2010-2011
Vessel: Magnificent
WD: 60 - 75 meters

Work Scope:

  • EPCIC for 5 new wellhead platforms
  • Detailed Engineering (by Consortium partner- Sime Darby)
  • Procurement and Fabrication (by Consortium partner- Sime Darby)
  • Transportation and Installation
  • Deck weights ranging from 1200 MT to 1320 MT each
  • Jacket weights ranging from 1340 MT to 1454 MT each
Client: ONGC
Project: MHNRD II Pipeline Project
Location: India
Period: 2011
Vessel: Swiber Conquest, Swiber Supporter, Swiber Atlantis
WD: 60 meters

Work Scope:

Engineering, procurement, transportation and installation of several pipelines and platform modifications

  • Laying of approx. 75.0km submarine pipeline in 14 segments for well fluid, gas lift, and water injection pipelines
  • Topside modification of 10 no. of existing well platforms (LA, NB, N1, NV, N6, NR, NW, NP, LC and WI-4) and associated modifications on NQP, NQG, proposed platform MNP and MNW process platforms
Client: ONGC
Project: North Tapti Gas Field Development
Location: Western Offshore India
Period: 2010-2011
Vessel: PJW3000
WD: 25 meters

Work Scope:

EPCIC for new wellhead platforms and connected pipeline to existing process platform on North Tapti Gas Field Development

  • EPCIC for 2 new wellhead platforms and 2 pipelines
  • Detailed Engineering (by Aker)
  • Procurement and Fabrication (by Consortium partner - Lamprell)
  • Procurement and Coating of Linepipe (by Swiber)
  • Transportation and Installation (by Swiber)
  • Jackets 536 MT each, Decks 840 MT each
Client: Santos (Sampang) Pty. Ltd.
Project: Wortel Field Development
Location: Indonesia
Period: FY2011-2012
WD: 42 meters

Work Scope:

  • Santos Wortel Jacket, Topside & Pipeline Installation Project
  • 3 leg Jacket(Piled Structure), 175 t deck, Oyong WHP modification Work, 10" x 9.6 km P/L)
Client: CNOOC/COOEC - China
Project: LF13-2 Pipeline Replacement Project
Location: CHINA
Period: FY2011
WD: 150- 160 meters

Work Scope:

  • Pipe in Pipe Installation of 11.50 KM (12"/16" ) Pipeline Installation
Client: ONGC
Project: B193 Process Platform
Location: India
Period: FY2011-2012
Vessels: PJW3000 & Swiber Conquest, Holmen Pacific & Holmen Atlantic
WD: 75 meters

Work Scope:

  • Design, engineering, procurement, fabrication, transportation, installation and commissioning of major platforms.
  • CPP jacket 6,400 MT, Deck 13,500 MT,
  • LQ Jacket 4,600 MT, Deck 7,200 MT
Client: ONGC
Project: Subsea Pipeline for B193 Project
Location: India
Period: FY2011-2012
Vessels: Swiber Conquest & Swiber Concorde
WD: 60 meters

Work Scope:

  • EPCI (engineering, procurement, construction and installation) of seven segments of pipelines ranging from 8" to 16" over a total length of 116.5km.
  • Also in the scope are modification works for the BCP-B platform and tie-in with ICP Heera trunkline, laying of 24.5 km subsea composite cable from B-22A to B-193A, laying of 8" x 2.744 km length of subsea flexible pipeline, tie-in of 16" rigid pipeline from B-22 to B-193A with pre-installed riser at B-193A jacket.
Client: Brunei Shell Petroleum
Project: Inspection, Repair, and Maintenance Contract
Location: Brunei
Period: 2010-2014

Work Scope:

  • Saturation Diving System Supply of equipment and personnel for BSP for ERM work in its offshore facilities
Client: Brunei Shell Petroleum
Project: Cable Replacement Project
Location: Brunei
Period: FY2011-2012

Work Scope:

  • 7 Cables Installation, J-tube , Riser Installation
  • Work Scope: Receiving & transportation of cables, Installation of clamps, I/J tubes & crossings etc.
Client: Brunei Shell Petroleum
Project: Brunei Shell - CPNQ-07
Location: Brunei
Period: FY2011-2012
WD: 50 meters

Work Scope:

  • Transportation and Installation of New Champion 7 Living Quarters (CPNQ-07).
  • Jacket Weight - 1500 MT
  • Deck Weight -700 MT
Client: Pearl Oil/MEINDO
Project: Ruby Field Development Project
Location: Indonesia
Period: FY2011-2012
WD: 0-90 meters

Work Scope:

  • Installation of 305KM , 14" pipeline including beach pull & Onshore preparation & laying.
Client: ConocoPhillips Indonesia
Project: Bawal Field Development
Location: Indonesia
Period: FY2011-2012
WD: 90 meters

Work Scope:

Phase 1:
  • Installation of 7.35 km umbilical from Hang Tuah platform to SDU 2
  • Installation of 8" x 800 m flexible pipeline from T8 well to Manifold
  • Topside modification works
Phase 2:
  • Installation of 34 km umbilical from SDU2 to UTA
  • Installation of tie-in spools and pre- commission works
  • Topside modification works
Client: ESSAR/ONGC
Project: D-1 Field Development Project
Location: India
Period: FY2011-12
WD: 85 meters

Work Scope:

  • Installation of 3 WH Jackets (1996 MT, 2230 MT & 2335 MT), 3 WH Platform Decks (2030 MT, 2 x 2033 MT) and one bridge (300 MT) in D-1 Field Development Project.
Client: PTTEPI
Project: Zawtika Offshore Pipeline Installation
Location: Myanmar
Period: FY2011 - FY2013
WD: 160 meters

Work Scope:

  • Installation of 28" x 230 km gas export pipelines sized for 600 MMSCFD, connecting between ZPQ process platform, though Block M10 to landfall close to Mawgyi village, nearby existing Yadana and Yetagun lines and about 3-4 km south of Daminseik village
Client: PVC-MS
Project: Block 16-1 Te Giac Trang Field Development Project
Location: Vietnam
Period: FY2012
Water Depth: 40 - 50 m

Work Scope:

  • Transportation and installation of H4 Topsides (2320 MT)
Client: Total E&P Indonesie
Project: Sisi Nubi Phase 2B & Peciko Phase 7B Development Project
Location: East Kalimantan, Indonesia
Period: Q2/Q3 2013
Value: US$77M
Water Depth: 40 - 70 meters

Work Scope:

Transportation & Installation of new facilities including:

  • WPS2 Quadripod Jacket Structure (1400 MT)
  • WPS2 Platform integrated topsides (1350 MT)
  • WPN3 Tripod Jacket structure (820 MT)
  • WPN3 Platform Integrated Topsides (900 MT)
  • SWP-J Tripod Jacket Structure (750 MT)
  • SWP-J Platform integrated Topsides (840 MT)
Client: Total E&P Myanmar
Project: TEPM Yadana Subsidence Project (YSP)
Location: Myanmar
Period: FY2012-FY2013
Water Depth: 45 m

Work Scope:

Transportation and installation of FP2, QP2 and Ancilliary structures:

  • MCP N-W Module (150 MT)
  • MCP S-W Module (31 MT)
  • MCP-FP2 Bridge (350 MT)
  • FP2 Tripod Jacket (600 MT)
  • PP N-W Module (35 MT)
  • QP2 Jacket (1986 MT)
  • QP2 Boat Landing (132 MT)
  • Main Support Frame-2 (1615 MT)
  • PP-QP2 Bridge (260 MT)
  • QP2 Module (2036 MT)
Client: PEMEX Exploration and Production
Project: Dos Bocas Line 5 Project
Location: Gulf of Mexico
Period: Q1 2012 - Q1 2013
Vessels: Swiber Concorde and Aziz
WD: 26.2 meters

Work Scope:

  • Procurement and Construction of 36" x 77 Km. of Coastal Linking Platform to TMDB (Line 5 ) Offshore Pipeline including HDD shore approach and onshore tie-in